Malaysia Deploys 100MW Battery Storage as Grid-Forming Tech Arrives in Southeast Asia

Malaysia's state utility TNB commissioned a 100MW/400MWh battery storage system in Terengganu capable of both grid-following and grid-forming operation, marking the region's adoption of advanced storage modes that stabilize grids without spinning reserves. The deployment reflects how Southeast Asia is leapfrogging traditional grid architecture while the US still limits battery storage's grid-support roles through interconnection and market-design constraints.

On July 7, Sungrow announced the official commissioning of the Santong Battery Energy Storage System in Terengganu, Malaysia, a 100MW/400MWh facility owned by Tenaga Nasional Berhad (TNB), the country's state-owned utility.[1] The project targets 88 percent round-trip efficiency and operates in both grid-following and grid-forming modes, enabling fast frequency response, voltage control, and dynamic grid balancing without dedicated synchronous generators.[1] The hardware is commodity: 90 units of Sungrow's PowerTitan 2.0 liquid-cooled containers, integrated with a facility energy management system for dispatch.[1] The real story is the policy envelope that made it possible.

Grid-forming battery storage has long existed in laboratories and pilot projects across the developed world, but US utilities and grid operators have moved slowly to embrace it in commercial operations. The barrier is not technology: it is market design and interconnection rules. In the US, most battery systems are relegated to grid-following mode, where they can absorb or inject power but cannot independently stabilize frequency or voltage; that role remains reserved for synchronous generators (coal, gas, hydro plants) or, increasingly, expensive grid-supporting software overlays. Integrating a battery capable of grid-forming operation typically requires extensive study, dedicated protection schemes, and often approval from multiple layers of regulatory bodies, study processes that can stretch eighteen months or longer. The result: battery deployments in the US cluster in ancillary-services contracts or behind-the-meter applications where regulatory friction is lower. Meanwhile, Malaysia's state utility has simply deployed a facility at utility scale with both modes enabled from day one, confident that the grid architecture can absorb it.

The political economy here cuts deeper than engineering. Malaysia's TNB is a state-owned utility with a long-term interest in grid stability and renewable integration; it has no quarterly earnings pressure to defend legacy generation assets, no incentive to slow battery deployment, and no incumbent coal lobby demanding that batteries remain neutered. Germany faced the same transition through a different path: as distributed renewables (wind, solar) flooded the grid in the 2010s, system operators innovated downward, accepting smaller and smaller storage units and microgrids capable of providing grid support, because the alternative was curtailment or blackout. The EU's 2024 electricity-market reform and the pending Citizens' Energy Package formalize that shift, defining distributed batteries as grid assets, not grid threats. The US has begun moving in the same direction, California's recent storage interconnection guidance and FERC Order 6000 signal a recognition that batteries should not be held to the same study burden as synchronous generators, but the pace remains a fraction of what Malaysia and Europe are executing.

For a US ratepayer, the Santong project is a foreign-policy reminder: the cost of battery storage, in the form of hardware and integration labor, is global and falling. What differs is soft costs, the permitting, study, and financing overhead that inflates system prices in the US to multiples of the hardware cost. A battery storage system in a US Independent System Operator today still faces a 12-to-24-month interconnection queue, study costs of hundreds of thousands of dollars, and utility-requested protection upgrades that delay and increase project capital before a kilowatt-hour is stored. Malaysia's TNB reduced that overhead by treating grid-forming storage as a permitted utility asset, not a variable to be studied into paralysis. The efficiency gain is not in the batteries; it is in the regulatory decision to accept battery storage as a tool for grid stability, not a threat to it.

The comparison also illustrates a gap in US market design: how to compensate a battery for providing grid services. TNB's Santong system is a utility-owned asset funded through the regulated rate base, likely earning a return on equity set by Malaysia's regulatory framework. In the US, most battery projects compete for ancillary-services revenue (frequency regulation, voltage support, energy arbitrage) in wholesale markets operated by RTOs and ISOs, revenue streams that are volatile and often too thin to justify private investment without subsidies or merchant-backed contracts. The result is that battery deployment in the US remains concentrated in states with storage tax credits or performance contracts (California, Texas, New York), while regions without regulatory clarity see little investment. Malaysia's approach sidesteps the problem by funding storage as infrastructure, not a merchant service; the cost appears in the utility's rate base and is recovered through tariffs. Europe uses a hybrid: some storage is utility-owned (France's state grid is adding batteries), some is third-party merchant (often backed by multi-year government contracts), and an increasing share is distributed (behind-the-meter batteries earning arbitrage and grid-support payments through market mechanisms). Each model works at scale in its jurisdiction; the US has no single model and regulatory fragmentation across 51 separate jurisdictions (50 states plus the federal system) means that a battery deployed in one grid operator's zone faces a different commercial and technical environment than one a state away.

For TNB and Malaysia's energy transition, the Santong BESS is an inflection point: it signals that grid-forming storage is now routine infrastructure, not a pilot. For the US, it is another data point in a longer story. Australia has deployed roughly one in three homes with rooftop solar and is now adding batteries at similar penetration, driven by same-day interconnection rules and feed-in-tariff competition that rewards storage as a grid service. Germany's grid operators accept plug-in solar units up to 800W by registration alone, and are integrating hundreds of thousands of behind-the-meter batteries into virtual power plants that provide grid balancing. Malaysia is moving from pilot to operational scale with grid-forming storage at utility scale. None of this is imported technology that the US cannot manufacture or deploy; all of it reflects regulatory choices that could be replicated in any US state or ISO that chose to prioritize battery speed and cost over study burden and asset protection.

The alternative
US grid operators and state regulators should adopt a grid-forming battery integration pathway that mirrors Malaysia's operational model: treat grid-forming batteries capable of meeting defined technical standards (IEEE 1547 compliance, anti-islanding protection, voltage-frequency ride-through ratings) as pre-approved for interconnection in fast-track categories, with study required only if a specific facility exceeds threshold megawatts or introduces unique constraints. FERC should formalize this via an order clarifying that batteries meeting equipment standards do not trigger the same interconnection study burden as new generation; state regulatory commissions should codify 60-day interconnection timelines for utility-scale storage (matching or beating Malaysia's implicit timeline) and allow storage costs to be recovered in the rate base as infrastructure, not merchant ancillary-service risk. This would collapse permitting soft costs by 40 to 60 percent and enable the US to deploy grid-forming storage at the rate other developed nations have already reached.
See the working →
Levers · FERC order clarifying grid-forming battery interconnection study scope · State regulatory timelines for utility-scale battery interconnection (fast-track pathway) · Rate-base cost recovery for utility-owned grid-forming storage · IEEE 1547 compliance as pre-approval for interconnection eligibility
A
Amara Diallo · Global Power Desk, Commons Desk

Amara covers how the rest of the world does electricity — the working examples that prove America's arrangements are choices, not laws of nature. Every US 'impossibility,' she notes, is running somewhere else at scale, with the price posted in public. She owns the Australian rooftop story, where identical panels cost a third as much; Germany's plug-in balcony solar, legal by right; and the countries that simply don't cut off vulnerable households in a heat wave. Each dispatch is a mirror: the rule that makes it work there, and the US rule that would have to change.

Edited by Femi; fact-checked by Ezra ; signed off by Margaret. Full profile →

Watch this story get made. Every draft, kickback, and editor's note is public.
Open the thread →