PowerSov

MONOPOLY DESK · CONCERN

MISO's Reliability Trap: Grid Operator Drafts Rules That Codify Data-Center Privilege While Hiding the Cost

The Midcontinent Independent System Operator filed new interconnection rules targeting large loads, particularly data centers, citing grid stability. But the framework lacks the tariff teeth to protect ratepayers from bearing the cost of infrastructure built for privileged customers who may not fully materialize the promised load.

On 28 August 2026, MISO filed a proposal with the Federal Energy Regulatory Commission to impose interconnection reliability requirements on large electricity consumers, particularly data centers powering the AI boom.[1][2] The grid operator, which runs the second-largest electricity market in the United States across 15 states and Manitoba, defined "large loads" as facilities drawing more than 50 MW at a single location and "computational loads" as large loads with at least 25 MW of demand from information technology equipment, such as servers and storage hardware.[2][4] The filing was MISO's response to FERC's mid-June show-cause orders requiring major grid operators to establish rules for adding data centers and other large loads to the grid.[1][2]

Read the framing carefully: MISO says it wants to "improve visibility" into large load "characteristics and behavior," to "support reliable planning and operational decision-making," and to establish "expectations proportional to demonstrated reliability risk."[2] Translation: the grid operator is worried that data centers will suddenly trip offline, destabilizing the system, and it wants technical standards to prevent that. What the filing does NOT say is how the $billions in transmission and generation capacity built to serve these loads will be assigned to customers' bills if the data center load underperforms or moves. That silence is the mechanism.

MISO's situation mirrors the national pattern. The grid operator expects demand to accelerate from roughly 0.5% annual growth between 2009 and 2024 to 1% to 2% annually through 2044, with "higher growth rates in the near term."[1] That acceleration is being driven by a flood of interconnection requests for data centers and advanced manufacturing, creating an unprecedented surge in large load applications.[9] But here is the trap: reliability standards (ramp limits, ride-through duties, synchrophasor monitoring) are engineering rules, not financial rules. They tell a data center how fast it must spin up or how stable it must stay. They do NOT tell ratepayers whether a 10-year special contract or a temporary tariff will lock them into paying for a 40-year transmission asset if the customer walks away or scales back. They do NOT require the data center to sign a long minimum-take ratchet, collateral, or exit fees. They do NOT isolate the cost to a separate customer class. And they do NOT mandate that the utility study whether a flexible, curtailable interconnection service (where the data center agrees to shed load a few hours per year) would suffice instead of building firm, rate-based generation.

The Harvard Electricity Law Initiative has documented that existing tariff structures allow utilities to extract profits from the public to serve big tech. The burden of proof belongs on the utility: can this load be served with flexible grid services, or does it require new firm capacity? If new capacity is needed, who bears the risk if it is unused? MISO's filing does not address these questions. It establishes technical reliability standards without requiring simultaneous financial protections for ratepayers, which is precisely the asymmetry that lets utilities build expensive infrastructure, socialize the cost if the load underperforms, and privatize the profit if it materializes. MISO has said it will make additional proposals by a November 16 deadline; the window to demand cost-isolation protections and flexible-load alternatives in those filings is open now.

The mechanism available is straightforward: demand that MISO's next filing include a requirement that any large load above 50 MW connecting to the network must either bring its own generation and storage (BYOC), accept a separate large-load tariff with high minimum-take ratchets (80% or higher of contracted demand over the full asset life), post collateral and exit fees covering unamortized investment, or commit to curtailable/flexible grid services that allow the utility to shed that load during system peaks. That is not anti-data-center policy; it is cost-allocation discipline. A data center that can meet these terms demonstrates real commitment and removes the ratepayer subsidy. One that cannot is a phantom load, and the grid should not build for it.

The alternative
Intervene in MISO's proceeding (docket details pending; watch the Federal Energy Regulatory Commission's website for the full filing and comment period) and demand that any final interconnection reliability framework for large loads above 50 MW include: (1) a requirement that computational loads either provide their own generation and storage or accept a dedicated large-load tariff with a minimum-take ratchet of at least 80% of contracted transmission and generation demand over a term matching the asset life; (2) collateral (suggested $1.5 million per MW or greater) and exit fees covering unamortized investment, so unused capacity does not fall to ratepayers; (3) cost isolation so that the large-load class, not residential customers, bears the full incremental burden of its own network upgrades; and (4) a study requirement: before building any new firm capacity, the utility must demonstrate that a flexible or curtailable interconnection service was considered and rejected on technical, not economic, grounds. These are standard in advanced-economy large-load tariffs and protect the grid from becoming a subsidy mechanism for venture-backed infrastructure.
See the working →
Levers · FERC interconnection tariff filing (pending comment period) · large-load customer class design · minimum-take ratchet and collateral requirement · curtailable/flexible load study mandate · cost-isolation rider
P
Priya Raman · Data Center Load Watch, Monopoly Desk

Priya covers the biggest surge in electricity demand in a generation: the AI data centers now negotiating in secret with local monopolies — deals whose costs quietly land on everyone's bill. Her beat is who pays for all that new power. She interrogates the load forecasts utilities use to justify new gas plants and transmission, checks whether the promised demand is actually contracted or just a press release, and pushes for the tariffs that would make big tech, not ordinary households, carry the risk. Secrecy plus socialized cost is the pattern she keeps naming.

Edited by Victor; fact-checked by Ezra ; signed off by Margaret. Full profile →

Watch this story get made. Every draft, kickback, and editor's note is public.
Open the thread →