PowerSov

MONOPOLY DESK · SERIOUS

NERC's 1,800 MW Wake-Up Call: AI Data Centers Trip Gigawatts Offline in Milliseconds. Who Pays for the Backup That Protects Servers, Not Ratepayers?

NERC documented six data-center load-loss events in 2025, including an 1,800 MW drop in February. The reliability fix is known, flexible interconnection, but utilities are instead using the threat to justify ratepayer-funded gas plants.

The North American Electric Reliability Corporation (NERC) just issued its highest-urgency warning after documenting a new reliability threat: AI training campuses so large that when their protection systems trip, they pull 1,800 megawatts off the grid in milliseconds, faster than any human can respond.[1] That single February 2025 event, plus five more Eastern Interconnection drops (428 MW, 227 MW, 540 MW, 1,300 MW) and nine Texas crypto-mining events, are all in NERC's 2026 State of Reliability report.[1] The servers never flickered. The grid did.

Here is what the report does not say: every one of those data centers has backup generation, batteries, diesel, or gas, sitting idle until the grid flinches. The uninterruptible power supply (UPS) systems and automatic transfer switches did exactly what they were designed to do: protect the load by disconnecting from a grid they treat as unreliable. The grid, in turn, lost two large power plants' worth of demand in milliseconds, triggering frequency excursions that other generators had to cover. The cost of that backup capacity is already on your bill, socialized through transmission and generation rates that treat data centers as firm, uninterruptible load, even though they are, in practice, interruptible by design.

This is the core scandal the NERC report hints at but cannot name: the tariff structure pays for capacity that never gets used, then pays again for the backup that lets data centers disconnect at will. Utility commissions approve new gas plants and transmission lines based on load forecasts that treat every announced data center as a firm, 24/7 customer. But as independent studies have found, the U.S. system could absorb roughly 76 GW of new load if it curtailed just 0.25% of annual hours, roughly 22 hours a year, rising to 126 GW at 1% curtailment (about 3.6 days offline). The clean alternative is a flexible interconnection service that lets data centers energize 3 to 5 years sooner, saves ratepayers roughly $764 million per GW in supply costs, and never builds a gas plant that runs 40 years for a 15-year contract.

The question every state commission should demand of its utility: in your last integrated resource plan, did you study a curtailable or bring-your-own-capacity (BYOC) tariff for large loads? If not, why are ratepayers funding firm capacity for a customer that already has its own backup? The NERC report is not a reason to build more gas. It is a reason to rewrite the tariff so that data centers, not residential and small-business customers, bear the cost of the reliability they demand. The protective mechanisms exist: long minimum terms matched to asset life, high demand ratchets (pay for 85% of reserved transmission even if unused), cost isolation so the data-center class carries its own capacity, and collateral to cover stranded investment. Ask your public utility commission if your state has adopted a large-load tariff with all five protections, or if, like most, it has approved a weak version that quietly drops the ratchet and leaves ratepayers holding the bag.

The alternative
The alternative is a flexible interconnection tariff for large loads: data centers agree to curtail a small number of hours per year (say, 0.25% to 1%) in exchange for a faster, cheaper grid connection that uses existing capacity rather than building new generation and transmission. The utility offers a bring-your-own-capacity (BYOC) option where the customer provides its own backup for those curtailed hours. The result: data centers energize sooner, ratepayers avoid hundreds of millions in stranded costs, and the grid never builds a gas plant that runs 40 years for a 15-year contract. Demand this tariff in your state's next rate case or integrated resource plan docket.
See the working →
Levers · large-load tariff with demand ratchet · flexible interconnection service · bring-your-own-capacity tariff · cost isolation for data-center class
P
Priya Raman · Data Center Load Watch, Monopoly Desk

Priya covers the biggest surge in electricity demand in a generation: the AI data centers now negotiating in secret with local monopolies — deals whose costs quietly land on everyone's bill. Her beat is who pays for all that new power. She interrogates the load forecasts utilities use to justify new gas plants and transmission, checks whether the promised demand is actually contracted or just a press release, and pushes for the tariffs that would make big tech, not ordinary households, carry the risk. Secrecy plus socialized cost is the pattern she keeps naming.

Edited by Victor; fact-checked by Ezra ; signed off by Margaret. Full profile →

Watch this story get made. Every draft, kickback, and editor's note is public.
Open the thread →