Puerto Rico's Grid Stuck in Federal Limbo: $10.7 Billion Obligated, Almost Nothing Spent
Nine years after Hurricane Maria, the federal government has obligated $14 billion for Puerto Rico's grid recovery but disbursed only $3.6 billion. Bureaucratic delays, staff turnover, and broken coordination between FEMA, HUD, and the Department of Energy have left the island with the worst power reliability in the nation and ratepayers paying some of the highest rates in the country.
A Government Accountability Office audit released in July 2026 found that of roughly $14 billion obligated by federal agencies for Puerto Rico's grid recovery and modernization since Hurricane Maria in 2017, only about $3.6 billion has actually been disbursed [1][2]. FEMA alone has obligated $11.1 billion but distributed only $2.7 billion, leaving 249 projects "at different stages of completion" and just nine FEMA-funded projects fully completed as of December 2025 [1]. The promised reconstruction of the island's electrical grid, which suffered the longest blackout in U.S. history following Maria's direct hit, remains stalled by the same kind of federal machinery failure that leaves monopoly infrastructure aging across the mainland: bureaucratic gridlock, staff churn, and the absence of enforceable timelines.
The breakdown exposes a structural problem that extends far beyond Puerto Rico's immediate crisis. Vegetation management, the single largest source of outages on the island, illustrates the mechanism. About half of Puerto Rico's frequent outages are caused by vegetation growing too close to transmission and distribution lines [1]. Luma Energy, the island's private utility, estimated that clearing vegetation around power lines, substations, and facility access roads would cost $1.2 billion (about $1.2 billion USD). As of December 2025, FEMA had obligated only roughly $103 million for nine vegetation-clearing projects, despite Luma's submission of funding requests for 34 such projects [1]. The pace is glacial: only 400 of the 16,000 miles planned for vegetation clearing have been completed, roughly 2.5 percent [1]. Meanwhile, the utility's antiquated power plants cannot generate about a third of the electricity needed during peak demand [1], a constraint that amplifies every outage into a cascading loss of service.
This is not mismanagement of isolated federal aid. It is the same neglect pattern that shows up on mainland SAIDI and SAIFI records: infrastructure deliberately starved of maintenance spending, then rebuilt at public cost after failure. On the mainland, utilities collect depreciation allowances in rates for decades, underspend on the actual assets, distribute cash as dividends, and then petition for "hardening" surcharges to rebuild what should have been maintained [background library]. In Puerto Rico, the federal government plays the role of the underspendings utility: obligating billions while the island's grid continues to deteriorate, customers pay rates among the highest in the nation, and the authority responsible for distribution (LUMA) operates under a private management contract with no performance-based reliability mechanism holding it accountable [1][8].
The GAO audit names the culprits: FEMA's staff turnover and organizational dysfunction, complex environmental reviews, permitting delays, and the absence of a single coordinating authority across three federal agencies [2][4][8]. But the deeper issue is that nobody has skin in the game. FEMA is not penalized for slow disbursal. Luma Energy collects its management fee regardless of whether vegetation is cleared or plants are modernized. Puerto Rico's ratepayers, paying some of the highest rates in the country, have no leverage to force either party to perform. The island remains subject to rolling blackouts nearly a decade after a Category 4 hurricane, and a territory-wide blackout in April 2025 lasted nearly two days [4][6]. That is the floor of a system with no accountability mechanism.
The remedy requires what the mainland lacks and Puerto Rico can now build: a performance-based reliability standard with teeth. FEMA and the Department of Energy should impose explicit conditions on the remaining $10.7 billion: a binding schedule for vegetation clearing (with quarterly payment releases tied to miles completed); a specific SAIDI reduction target for each utility zone (with penalties for miss); and authority for the island's energy commission to impose penalties on Luma Energy if restoration times exceed a defined threshold. Britain's RIIO framework and Hawaii's 2020 performance-based regulation model show that revenue caps paired with symmetric reliability rewards and penalties remove the bias toward capital spending and toward delay [background library]. Puerto Rico's grid recovery should be conditioned on the same mechanism: LUMA's management fee and its capital allowance should be at risk against reliability performance, not guaranteed. Every month a vegetation project sits undisbursed costs the territory millions in lost economic output and forces ratepayers to absorb blackout costs that should fall on the entities collecting the fees.
[1] Washington promised Puerto Rico $14 billion to fix its grid. Most of the money is still stuck.
[3] Audit finds Puerto Rico awaiting billions of dollars after deadly 2017 hurricane | AP News
[4] Federal Aid Flows Slowly as Puerto Rico's Grid Recovery Lags
[5] Federal audit finds Puerto Rico awaiting billions of dollars nearly a ...
[6] El Apagón—The Blackout. Puerto Rico’s Continuing Struggle for Stable Electricity
[7] Only 25 customers still without power in Puerto Rico, nearly 11 months after Maria
[9] Night Lights Show Slow Recovery from Maria - NASA Science